logging


TERMINOLOGY
Like most professions, petroleum engineering is beset with jargon.
Therefore, it will make things simpler if I first go through some of the
basic terms that will be used throughout this book. Petroleum engineering
is principally concerned with building static and dynamic models of
oil and gas reservoirs.
Static models are concerned with characterizing and quantifying the
structure prior to any production from the field. Hence, key parameters
that the models aim to determine are:
STOIIP = stock tank oil initially in place; usually measured in stock
tank barrels (stb)
GIIP = gas initially in place; usually measured in billion standard cubic
feet (Bcf)
GBV = gross bulk volume; the total rock volume of the reservoir
containing hydrocarbon
NPV = net pore volume; the porespace of the reservoir
HCPV = hydrocarbon pore volume; the porespace actually containing
hydrocarbon
f = porosity; the proportion of the formation that contains fluids
k = permeability; usually expressed in millidarcies (md)
Sw = water saturation; the proportion of the porosity that contains water
Sh = hydrocarbon saturation; the proportion of the porosity that contains
hydrocarbon
FWL = free water level; the depth at which the capillary pressure in the
reservoir is zero; effectively the depth below which no producible
hydrocarbons will be found


HWC = hydrocarbon/water contact; the depth below which the formation
is water bearing as encountered in a particular well. Likewise,
OWC for oil and GWC for gas
GOC = gas oil contact; the depth below which any gas in the reservoir
will be dissolved in the oil
Gross thickness = the total thickness of the formation as encountered
in a particular well
Net thickness = the part of the gross thickness that contains porous rock
subject to given cutoff criteria
Pay thickness = the part of the net thickness that is considered to be
capable of producing hydrocarbons in a particular well
Because of inherent uncertainties in all the parameters used to determine
STOIIP or GIIP, geologists will usually develop probabilistic
models, in which all the parameters are allowed to vary according to distribution
functions between low, expected, and high values. The resulting
static models may then be analyzed statistically to generate the following
values, which are used for subsequent economic analyses:
P50 STOIIP: the value of the STOIIP for which there is a 50% chance
that the true value lies either above or below the value
P15 STOIIP: the value of the STOIIP for which there is only a 15%
chance that the true value exceeds the value. Often called the high case.
P85 STOIIP: the value of the STOIIP for which there is an 85% chance
that the true value exceeds the value. Often called the low case.
Expected STOIIP: the value of the STOIIP derived by taking the
integral of the probability density function for the STOIIP times the
STOIIP. For a symmetric distribution, this will equal the P50 value.
Similar terminology applies to GIIP.
In order to predict the hydrocarbons that may be actually produced from
a field (the reserves), it is necessary to construct a dynamic model of the
field. This will generate production profiles for individual wells, subject
to various production scenarios. Additional terminology that comes into
play includes:
Reserves = the part of the STOIIP or GIIP that may be actually produced
for a given development scenario. Oil companies have their own
rules for how reserves are categorized depending on the extent to which
they are regarded as proven and accessible through wells. Terms fre-
2 Well Logging and Formation Evaluation

quently used are proven reserves, developed reserves, scope for recovery
reserves, probable reserves, and possible reserves.
Remaining reserves = that part of the reserves that has not yet been
produced
Cumulative production = that part of the reserves that has already been
produced
UR = ultimate recovery; the total volume of reserves that will be produced
prior to abandonment of the field
NPV = net present value; the future economic value of the field, taking
into account all future present value costs and revenues
RF = recovery factor; the reserves as a proportion of the STOIIP
(or GIIP)
Bo = oil volume factor; the factor used to convert reservoir volumes of
oil to surface (stock tank) conditions. Likewise Bg for gas.
In order to produce the hydrocarbons, wells are needed and a development
strategy needs to be constructed. This strategy will typically be presented
in a document called the field development plan (FDP), which
contains a summary of current knowledge about the field and the plans
for future development.
Once an FDP has been approved, the drilling campaign will consist of
well proposals, in which the costs, well trajectory, geological prognosis,
and data-gathering requirements are specified. The petrophysicist plays a
part in the preparation of the well proposal in specifying which logs need
to be acquired in the various hole sections.

Mud Logging: Introduction

Logging System provides a full range of rig monitoring, data acquisition, mud logging and drilling engineering services. The Standard mud logging and rig monitoring services are based around our online computerized units (PSL system). Field Drilling Technique (FDT) and consultancy services (geologists, drilling and petroleum engineers) are available from PetroServices GmbH drilling services pool of experienced and qualified personnel.

Advanced computer systems with applications software augment these services. They can be offered as part of the well site and office based services with configuration to a Client’s specific needs. The online computerized unit (PSL system) can be installed in various forms depending on Client requirements. The PSL system is an intelligent, multi-tasking, real time data acquisition and monitoring system. It accepts inputs from all the sensors and provides real time monitoring with audio-visual alarms and error messages of parameters with output to 18” LCD & 20” Monitors, chart recorders, and printers.

All data variables and interval averages are directly stored in a non-volatile data memory buffer. These are accessed by the applications computers, for data manipulation, permanent data storage, plotting and running applications software (DPIC®).

The Online Server Network Station with DTCIS software® creates a comprehensive database of all drilling and geological parameters on 500 GB hard disk with floppy (1.44 MB) and DVD (8.5 GB) disk back up. Full database management and editing is effected and a range of application programs run to enhance analysis and data interpretation. Real time, color graphic displays are available with the Server Network Station. It displays and stores selected time based information at 2-second intervals.

The scope of the logging systems can be expanded through the transmission to a town office system. Data can be transferred via Dial up communications as well as LAN connections, or just by disc update in ASCII format. When rig operations dictate, printed reports and real time displays (graphic screens) can be produced in the Town office on call by the user. In addition, through batch transfer, time or depth related parameters, can be received on the office PC with full access to all applications software, including log plots, and data printouts. PS Field Staff highly trained, with expertise and experience provides the best in performance drilling. The personnel involved have many areas of expertise: geology, formation evaluation, drilling, pressure evaluation, electrical and Log analysis.